Restoring the golden age of travel

1894

East Coast Joint Stock 189

Built in Doncaster and designed by David Bain for the East Coast Joint Stock. One of a batch of four (188, 189, 222, 223). 52ft 6in long, ~27 tons. Three saloons seating 42 in total. Ran coupled to a kitchen car — no cooking facilities of its own.

c.1900

189 in service, c.1900

A photograph taken around 1900, brought to life. At this time 189 was still in its original 1894 form: three gas-lit saloons seating 42, running alongside a kitchen car on the London to Edinburgh route. In 1909 it was refitted into the layout being restored today.

1909

Refitted – the 1909 configuration now being restored

Pantry added, 9 seats removed, three saloons reduced to two (seating 33). Side gangways replaced with Pullman gangways; gas lighting replaced with electricity.

1923

Grouping — No. 189 becomes LNER 1189

The three East Coast companies merge into the London and North Eastern Railway. In later years 1189 was likely used as a bar car serving drinks from the pantry.

1927

Withdrawn — body sold and installed as a dwelling

Body removed from its chassis and moved to Bellcross Lane, Howden, East Yorkshire. Known as Mazel Villa, owned by Bertram Percy Stone (WWI veteran, born Hull 1877). Original underframe lost at this point.

1962

Bertram Percy Stone passes away

The dwelling at Bellcross Lane passes to the Treasury Solicitor.

1964

Auctioned — sold to Richard Skowronek

Advertised in the Hull and East Yorkshire Times (26 Sept 1964) as a bungalow with living room, kitchenette, cloakroom, storeroom and bedroom. Purchased by local butcher Richard Skowronek.

1965

Planning appeal saves the carriage from demolition

Skowronek applied to redevelop the site. Council refused. He appealed; Minister of Housing Richard Crossman upheld the refusal. The carriage was saved.

1988

Moved to Holme-on-Spalding-Moor — pub restaurant plan falls through

Owner Malcolm Ford relocates the body with plans to use it as restaurant seating alongside a pub. The project never comes to fruition.

1990

A chassis purchased and early restoration begun at Holme-on-Spalding-Moor

Some work starts but the project stalls. By 1998 the carriage is outside and deteriorating badly.

1999

Rescued by Stephen Middleton — one week from destruction

Ownership transferred to carriage enthusiast Stephen Middleton. Chassis and body moved to the Yorkshire Dales Railway at Embsay; external restoration recommences.

2003

Displayed at the Wabtec works open day, Doncaster

Shown at the ‘Plant 150’ exhibition, demonstrating progress on the external restoration.

2005

Sold to Doncaster College as a planned classroom

Budget cuts scupper the plan. The carriage is left outside with no roof vents — serious water ingress results.

2009

LNERCA intervenes and moves the carriage to Pickering

A turning point — the restoration project that would become the charity’s flagship begins.

c2010 – 2014

Heritage Lottery Fund grant secured — major engineering challenge identified

The screw-coupled underframe must be replaced with a buck-eye type for NYMR operations. New solebars fabricated by Teesside Components. Institute of Rail Research at Huddersfield acts as independent quality assurance body.

2015

Arrives in the Atkins shed at Pickering

As a result of being abandoned in Doncaster the roof had suffered serious damage and needed some remedial work

2015

Stripped back

External panels removed and the roof all taken off ready to be replaced with a new roof

2018

Swapping the chassis

With the roof timbers now in place 189 was rolled out onto the turntable to enable the new chassis to be put into the shed.

2018

A new chassis

The original chassis was not saved when the carriage came out of traffic. A new one had to be acquired and shortened.

2018

Frame repairs

The teak panels were removed revealing that some of the iron knees needed repairing.

2018

Teak panels are applied

A combination of original panels and teak rescued from the S.S. Pegu are used.

2019

Interior fitting out begins

Once the roof and outside panels have been replaced work on the internals can begin.

Aug 2019

External signwriting

Completed by one of the volunteers’ sons. Not bad for a first attempt.

Sep 2019

Internal fitout

Work begins in earnest internally.

2024/2025

Roof painted and chimneys applied

Multiple coats of Durashield are applied to the roof sections to make it watertight. Torpedo vents and chimneys are fixed.

2025

Guttering fixed to the roof.

The roof has two sets of teak guttering on the roof. Each has then had beading applied.